Calculate

Calculate

Measurements convert when you switch units

m
m
m
m
m
m
m
t/m³
%

Updates as you type

Result

The formula

Rectangle: length × width × depth. Circle: π × (diameter/2)² × depth. Trench: length × trench width × trench depth. Weight = volume × sand density.

V = L×W×D · V = π(d/2)²×D · V = L×Wₜ×Dₜ · Order = V×(1+waste%) · Weight = V×ρ

Worked example

  1. Bedding area 10 m × 4 m × 0.05 m → base volume 2.0 m³
  2. Add 10% waste → order volume 2.0 × 1.10 = 2.20 m³
  3. At density 1.5 t/m³ → estimated weight 2.20 × 1.5 = 3.30 t

Result: 2.20 m³ to order (about 3.30 t)

How sand quantity is calculated

The calculator computes geometric volume first, then applies waste factor and density to estimate order weight.

Use compacted target depth

For bedding and sub-base work, enter the compacted design depth. Loose sand can settle after leveling and compaction.

Waste factor depends on site conditions

Rough ground, edge trimming, and handling losses increase required quantity. Typical waste factors are 5–12%.

Density varies by moisture and grain size

Dry fine sand and wet coarse sand can differ in bulk density. Use your supplier value when available.

Interesting facts

1 m³ is about 1.308 yd³

Showing both metric and imperial units helps when suppliers quote in different systems.

Typical sand density range

Bulk density often falls around 1.4–1.7 t/m³. This calculator defaults to 1.5 t/m³ for planning.

Moisture changes delivered mass

Wet sand is heavier than dry sand for the same volume, which affects transport weight and truck loading.

Bedding layers are usually thin

Paver bedding is often around 30–50 mm; over-thick layers can reduce stability if not compacted properly.

Trench fills are rarely perfectly rectangular

Irregular trench sides and local settlement can increase real demand over theoretical volume.

Small-load delivery charges are common

Converting volume to tonnes helps compare supplier minimum loads and transport costs.

Frequently asked questions

Use rectangular mode with bedding depth (often 0.03–0.05 m), then add a waste factor for leveling and handling.

Use compacted design depth for takeoff. If you only know loose depth, adjust order volume upward.

Tonnes = order volume (m³) × density (t/m³). Example: 2.2 m³ × 1.5 = 3.3 t.

Use about 5% for simple flat jobs, and 8–12% for irregular areas or trench work.

Yes. Use circle mode and enter diameter plus depth.

Yes. Subtract occupied volume/area so the order estimate matches actual fill needs.

Compaction and moisture settlement can reduce loose layer height after placement.

Yes, but set density to match material type and moisture condition from your supplier.

References

  1. Aggregate and sand guidance — UEPG Material use and properties for construction aggregates.
  2. SI units and conversions — NIST Unit conversion reference.

For planning and estimation only. Confirm design depth, compaction method, and local project requirements before ordering.

Last reviewed: 2026-08-16 — Reviewed by: Editorial Team